Ecosse Subsea Systems cleans up on Laggan-Tormore seabed route

Friday, Oct 05, 2012

-       67km route cleared at depths of 640 metres -

Ecosse Subsea Systems has completed a major seabed clearance project on the Laggan-Tormore project west of Shetland on behalf of TOTAL E&P Ltd and its partner DONG E&P (UK) Ltd.

The Aberdeen subsea technology company deployed its SCAR1 trenching tool to remove up to 1000 boulders which were delaying progress on cable laying and umbilical installation work.

The SCAR1 cut a 10 metre wide swathe over a 67km route, displacing boulders up to two metres in diameter and removing soil to leave a flat seabed for pipe laying to commence.

Typically seabed clearance is done using a ‘boulder grab’ device and is a slow process as it displaces rocks one by one, with operators reluctant to tackle boulders larger than a half metre in size.

The SCAR system was originally developed as a subsea plough but was redesigned and fabricated to suit TOTAL’s requirements and mobilised within a ten day window. The clearing plough worked at depths of 640 metres, believed to be a record for this type of equipment, and at optimum performance was clearing up to 1000 metres of seabed per hour.

Ecosse Subsea Systems managing director, Mike Wilson, said he hoped the success of the project has created a fresh solution for other exploration companies faced with complex seabed clearance issues.

He said: “Boulder clearance during seabed preparation is a real problem for some operators and is so arduous and expensive that often they opt to move the route of the pipeline. Our method, including preparation, vessel charter and deployment is considerably less expensive than the traditional alternative methods.

“Our SCAR system is extremely robust, easily mobilised, can work in the harshest environments and in up to depths of 3000 metres. The success of this project has demonstrated there is a much more efficient and less costly way of tackling seabed clearance and we anticipate this will lead to work on similar projects in the North Sea and other major oil and gas producing regions.”

 

Issued on behalf of Ecosse Subsea Systems Ltd by Sure Public Relations

posted in:

Other Subsea News

InterMoor Inc. enhances service with DNV certification for mooring chain inspections 20-06-2013
Karoon announces north Carnarvon Basin permit WA‐482‐P 3D seismic acquisition survey 20-06-2013
Ithaca Energy Inc. announces Stella field development drilling commences 20-06-2013
Reef Subsea secures subsea construction contract on Palanca Cable Lay Campaign offshore West Africa 20-06-2013
CARIS to host 15th international user group conference in France 20-06-2013
Aker Solutions delivers Åsgard template to Statoil 20-06-2013
Seatronics announces large purchase of advanced sonar equipment & new sales representation with EdgeTech in the Middle East 19-06-2013
Reef Subsea secures subsea construction contract on Palanca Cable Lay Campaign offshore West Africa 19-06-2013
Viper Subsea selected for Accelerate 2013 19-06-2013
Aker Solutions delivers Åsgard template to Statoil 19-06-2013